A depot that electrified its fleet without waiting for the grid

The local grid was congested and a bigger connection was years away. A battery let the depot charge 24 vans on the connection it already had.

Vans charged
24
Connection
400 kVA
Battery
300 kW / 600 kWh
Time saved vs grid queue
~2 yrs
The site
Regional logistics depot with a 400 kVA connection, moving to an electric van fleet.
The constraint
Grid congestion. The network operator put the request for a larger connection on a waiting list with no date.
What we modelled
Charging schedules for 24 vans across shift patterns, a rooftop PV array and battery sizes against the fixed 400 kVA limit.
What we chose
250 kWp PV, a 300 kW / 600 kWh battery and smart charging that never lets the site exceed its contracted capacity.
What we advised against
Waiting for the upgrade, or a diesel generator on site, which the municipality would not have permitted.
The return
The full fleet charges overnight within the existing connection. Electrification went ahead two years earlier than the grid timeline allowed.

The question

Could the depot electrify its fleet now, on a connection that was too small on paper?

What we did

We modelled every van’s route, arrival time and state of charge, then let the battery and charging controller share the 400 kVA. The binding constraint was a few winter evenings, not the average day, so the battery was sized for those.

What changed

The fleet runs electric today. When the larger connection arrives, the battery moves from enabling the site to earning from flexibility.