A cold store that stopped paying for its worst half hour
Peak demand charges were rising faster than the business. We modelled 14 configurations and specified a smaller battery than the one first quoted.
- Peak import cut
- 31%
- Simple payback
- 5.8 yrs
- Configurations modelled
- 14
- Connection upgrade avoided
- 1.5 MVA
- The site
- Cold-storage distribution centre with 1.5 MVA import capacity and refrigeration running around the clock.
- The constraint
- Red-band demand charges and a capacity limit that blocked new chiller lines without a costly connection upgrade.
- What we modelled
- 14 PV and battery configurations against 24 months of half-hourly data, three tariff scenarios and a chiller expansion in year two.
- What we chose
- 400 kWp rooftop PV with a 500 kW / 1,100 kWh battery, controlled to hold import under a fixed ceiling.
- What we advised against
- A 1 MW / 2 MWh containerised product quoted by a supplier. It cost 70% more and added little saving beyond the first 1,100 kWh.
- The return
- Peak import fell 31%, the chiller expansion fitted under the existing connection, and simple payback is 5.8 years.
The question
The client had a quote for a battery. They wanted to know whether it was the right size before signing a contract worth more than the site’s annual energy bill.
What we did
We took two years of half-hourly meter data and rebuilt the site’s demand day by day, including the chiller line planned for year two. Each configuration was run against three tariff futures. The result was a clear knee in the curve: past about 1,100 kWh, every extra kilowatt-hour of storage saved almost nothing, because the site’s peaks are short and sharp.
What changed
The specification went out to three suppliers with a fixed control strategy written in. The site now holds its import under a ceiling, and the chiller expansion went ahead without a connection upgrade.
- Feasibility and sizing
- Business case
- Controls and EMS
- Specification and handoff